As always, these are just introductions and overviews, not legal advice. If you have specific questions, or need a new contract, talk with a lawyer. I am a Massachusetts attorney and I default to Massachusetts law; some of the information in my blog posts will inevitably be incorrect in other places. Due to the requirements under the various state statutes that set the rules for mechanic’s liens, it is possible to lose the right to file one by failing to take timely actions and missing a deadline, therefore if you believe that you will need to use this process, please consult a lawyer in your state without delay.
What is a Mechanic’s Lien?
A mechanic’s lien is a lien against a property (a building or land) that secures payment for work done on that property. In extreme cases, the party to whom payment is owed may foreclose on the property and force a sale to recover payments.
Traditionally, these liens have been used by contractors against nonpaying owners. However, in Massachusetts a failure of payment is not a prerequisite to a mechanic’s lien filing. Instead, a party that is eligible to file a mechanic’s lien may do so at any time prior to certain deadlines that relate to the dates when the work was performed and the substantial completion date.
How Does This Apply to Architects?
For simplicity, I’m going to refer to the “architect” here, but this applies to whatever design professional has the prime contract with the owner - so an interior designer, engineer, etc., who contracts directly with an owner has similar rights (but check with your lawyer if you are unsure whether this applies to you!)
An architect may unilaterally file a mechanic’s lien when the following requirements are met:
- The architect and the owner have a written contract for design services. This is one of many reasons why I advise architects to always use written contracts.
- The architect files a notice (more on that below) before (i) 60 days after substantial completion or (ii) 90 days after the architect or any of the architect’s employees, consultants or other parties under the architect’s direction last performed services on the project - whichever comes first.
- The architect notifies the owner directly that the lien has been filed.
Then What?
The lien, on its own, doesn’t do much. Notice that the filing in the registry does not have to include a statement that payments are owed, and may be filed as a matter of formality even before any design services are performed, so long as there is a written contract between the architect and the owner.
If the architect wishes to make the lien enforceable against the owner, the architect must make a second filing at the registry of deeds. This second filing identifies the owner and property, and contains a statement of the amount due and any credits. The deadline to file is (i) 90 days after substantial completion or (ii) 120 days after the architect or any of the architect’s employees, consultants or other parties under the architect’s direction last performed services on the project - whichever comes first.
The second filing is critical, because if the architect does not make this second filing, the lien is automatically dissolved and the architect loses it entirely.
What You Get For All This
If the architect has made all of the appropriate filings and the owner has failed to make payments, the architect may go to court to request a judicial foreclosure on the property. Many architects would consider that a drastic action and would strongly prefer to stay out of court. Even so, the lien gives the architect some strategic or tactical advantages:
- The fact that the architect has the right to sue is strong leverage against a delinquent owner.
- If the owner sells the property before the architect is paid, the lien follows the property. The effect of this is that a purchaser of the property is likely to demand that the owner pay the architect as a condition to the sale.
- If the owner declares bankruptcy, the lien gives the architect a stronger position than that of an ordinary creditor and makes it more likely that the architect will collect payment.
Design professionals working as consultants for architects may also file mechanic’s liens, provided that a few conditions are met:
- The architect (or whichever design professional has the prime contract) must be eligible to file a mechanic’s lien. This means that the architect must have a written contract and the deadlines must not have passed.
- The owner must have approved the use of the consultant in writing. Your lawyer will need a copy of the architect’s contract with the owner and any other written correspondence relating to consultants to ensure that the architect has the owner’s approval to hire consultants.
- The consultant must include the contract price or an estimate of the cost of the consultant’s work, as well as payments already received, when filing the lien.
- The consultant must notify the owner directly that the lien has been filed.